Equipment electrical maintenance knowledge

0.25T induction melting furnace installation instructions

Time: 2019-07-05

4.1. The installation of the equipment shall be carried out according to the floor plan and the basic drawing;

4.2. After installation, first check whether the grounding of the hob is good, and the grounding resistance should be less than 4Ω;

4.3. Check the insulation resistance between the conductive plate of the inductor and the metal of the furnace before passing through the water: measured by 2500V megohmmeter, it should be greater than 2MΩ;

4.4. Connect the cooling water into and out of the water pipe, and set the temperature control point of the bimetal thermometer to 55 °C;

4.5. Check the electrical control circuit of the reducer, tilt the furnace after error, and check whether the drive is flexible and normal;

4.6. No-load transmission to induction, the voltage from bottom to high to the rated value, inspection of components and sensor vibration;

4.7. After the above checks are correct, the mold can be hung from the mold to start the furnace.