Introduce:3-layer PE pipeline anti-corrosion production line, 3-layer PE anti-corrosion pipeline production line, providing design basis for pipeline steel pipe 3-layer PE anti-corrosion production line, steel pipe 3-layer PE anti-corrosion production line medium frequency heating system configuration selection method, steel pipe 3-layer PE anti-corrosion production line extruder Selection method
  • Introduction
  • Consultation


the project content:

Ф219—Ф1219 steel pipe 3-layer PE anti-corrosion production line

 Ф219-Ф1219 steel pipe, steel pipe 3-layer PE anti-corrosion production line design basis:

Steel pipe diameter: Ф219—Ф1219

Steel pipe length: 8000 mm -12000 mm

Process speed: 800 mm / min - 5000 mm / min

2_看图王.jpg

 the pipeline conveyor

According to the user's request , our company's Ф219-Ф1219 pipeline anti-corrosion production line is designed as a transmission line with a single wheel as the power unit.

 Ф219-Ф1219 steel pipe, steel pipe 3-layer PE anti-corrosion production line derusting machine:

New steel tube blast cleaning equipment, can remove rust and scale steel surface, fully meet the requirements of clean steel tube before the coating shoe, which can meet the large and medium-sized steel tube cleaning project needs.

 Ф219—Ф1219 steel pipe, electrical description of 3-layer PE anti-corrosion production line

The main circuit of the system is powered by AC three-phase 380V , the control system is provided by the transformer , and the AC 220V power supply .

This centralized system control electrical components mounted within the cabinet, the short circuit protection circuit breakers, motor overload protection provided by the thermal relay. On the platform over the inner tube with a purge and recovery, the splash into the inner tube derusting The steel grit and rust dust are purged .

 Ф219—Ф1219 steel pipe, steel pipe 3-layer PE anti-corrosion production line IF heating system configuration selection :

This production line is equipped with 750KW (user-supplied) and 1000KW two IF heating equipment for heating .

Ф219—Ф1219 steel pipe 3-layer PE anti-corrosion production line select 1000kw medium frequency induction heating power supply parameters:

name

parameter

name

parameter

Input voltage

380V

Output maximum voltage

780V

Input Current

1700A

Output maximum current

2000A

Input frequency

50HZ

Output frequency

500HZ~800HZ

219—Ф1219 steel pipe 3-layer PE anti-corrosion production line powder spraying system selection method

8 gun control center DK type 4 sets

Each apparatus having the above automatic gun 8, a high-pressure spray gun is built, control cabinet 8 controls automatic spray gun voltage, current and gas system. 8 and controls the Venturi system for the powder for the powder pump.

Each set of the above devices contains a fluidized bed powder supply system. The size of the fluidized bed: (L × W × H) 800 × 775 × 570 (mm) contains 8 venturi powder pumps .

 Ф219-Ф1219 steel pipe 3-layer PE anti-corrosion production line air compressor and water sprinkler system:

The production line is equipped with a 6-cubic screw air compressor , a 6-cubic air dryer , and a 1.0-cubic gas storage tank for powder spraying equipment (with 3 filters) . The water sprinkler system is open and convenient. Adjustment of the roller table .

With equipment details and price list:

 Ф219—Ф1219 steel pipe 3-layer PE anti-corrosion production line water cooling room:

Using water-cooled steel chamber windows closed, elegant, easy to observe. Each side windows do have several activities, easy access to cooling water pump 150 cubic meters per hour flow rate using two sets. In addition two sets of intermediate cooling water pump, the flow rate per hour 25 cubic meters coolingwater regulating valve is fitted in the side of the operation panel for easy adjustment. (in addition to the pump, the rest produced by the user).

air compressor and pipe mechanism:

 breaking machine, lift and secondary descaling machine:

 the release platform

 manufacturing and installation schedule

The production period is 55 days from the date of entry into force of the contract , and the installation period is 20 days (installation conditions are available) .